This document reviews the scope of services that the Loudoun County contractor will be undertaking.

Preliminary Engineering Services to "Bury the Wires and Tame the Traffic"
Waterford, VA

SCOPE OF SERVICES (Loudoun County RFP QQ-00963)

Introduction: The Consultant will provide professional engineering services to conduct investigations, perform preliminary engineering studies, and develop concept designs to "tame the traffic," bury overhead utility wires, and improve drainage in Waterford, while preserving and enhancing the historic character of the Village. Project Goal: To develop a set of practical, preliminary solutions that will provide the Village of Waterford with a master plan to take the next step in the planning and design process.

Kimley-Horn Team:

  • Kimley-Horn and Associates (Lead/Traffic/Roadway)
  • Walkable Communities (Planning)
  • B2E Consulting Engineers (Electrical)
  • William H. Gordon Associates (Civil)
  • Williamsburg Environmental Group (Environmental)
  • The Louis Berger Group (Historical)

Background:

  • National Historic Landmark District, Virginia Landmark Historic District, and a Loudoun County Historic District
  • Challenges with traffic growth in Loudoun County
  • Desire to relocate overhead utility wires and improve storm drainage
  • Need for an overall master plan to take to the next steps in funding process

Study Tasks:

Task 1 Data Collection: Mapping/GIS, traffic, utilities, stormwater, roadway, lighting environmental, historical resources, etc.

Task 2 Engineering Studies:

  • Traffic Calming Alternatives
  • Electrical/Telephone Utilities Alternatives
  • Utility Stormwater Drainage Alternatives
  • Roadway Alignment Alternatives
  • Environmental and historic resources considerations / review

Task 3 Preliminary Master Plan Concepts

Task 4 Design Workshop with Village Representatives, County, VDOT

Task 5 Public Presentation Meeting

Task 6 Final Design Alternatives Report - Master Plan Concepts

Schedule:

  • Feb. - Mar 03 Kick-Off Meeting / Public Meetings / Data Collection / Engineering Studies
  • Apr - Jun 03 Concept Designs and Design Workshop / Opinions of Construction Cost
  • Jul 03 Public Presentation Meeting and Final Report

 

 Top of page

 

 

 

| Home | Site index |

| Waterford historyleave this site | Loudoun historyleave this site |

 

 

 

 

traffic, bury wires, traffic calming, roads, esthetics, burying overhead wires, automobile spped reduction, waterford, va, virginia, waterford va, historic towns, loudoun county, civil war towns, villages, village, national historic landmark

space space
space
space